Payra Port — Rabnabad Channel Road & Bank Protection
Construction of road along the Rabnabad Channel with river-bank protection under the Payra Port First Terminal Project, Lot-03, chainage 04+400 to 06+600 m.
Evidence statusCompleted-work record cross-checked against the supplied project schedule. · Last verified 8 September 2026
CLIENT / AUTHORITY
Payra Port Authority
LOCATION
Patuakhali, Barishal
SCOPE
Construction of road along the Rabnabad Channel with river-bank protection under the Payra Port First Terminal Project, Lot-03, chainage 04+400 to 06+600 m.
DELIVERY STATUS
Completed
COMPLETION DATE
25 October 2024
CONTRACT VALUE
BDT 447,486,434.10
DG BANGLA / FIELD DOCUMENTATION
Road construction and river-bank protection along the Rabnabad Channel under the Payra Port First Terminal Project, Lot-03 (chainage 04+400 to 06+600m).
DG BANGLA / FIELD DOCUMENTATIONDG BANGLA / FIELD DOCUMENTATIONDG BANGLA / FIELD DOCUMENTATIONDG BANGLA / FIELD DOCUMENTATIONDG BANGLA / FIELD DOCUMENTATIONDG BANGLA / FIELD DOCUMENTATIONDG BANGLA / FIELD DOCUMENTATIONDG BANGLA / FIELD DOCUMENTATIONDG BANGLA / FIELD DOCUMENTATIONDG BANGLA / FIELD DOCUMENTATIONDG BANGLA / FIELD DOCUMENTATIONDG BANGLA / FIELD DOCUMENTATIONDG BANGLA / FIELD DOCUMENTATION
Record source: DGB Work List.pdf — entry 01, profile page 23